#MeasureS Update:
CANYON HS: The bid opening has been slightly pushed back to April 17, 2019. Proposed bid award is scheduled for Board review on May 9, 2019.
EL MODENA HS: Mobilization has begun at El Modena for the Science Center project with construction starting in mid-April. Groundbreaking Ceremony happening tomorrow (4/13)!
ORANGE HS: Demolition and Site Prep continues for the OHS Science Center. With the demolition of the old snack bar, the site is now ready for excavation.
VILLA PARK HS: Students began classes in the new portables on April 8, 2019. In addition, a new driveway was added on Taft Avenue to prepare for the demolition of Building 300.